- The Smart Cities Mission (SCM) was launched by the Government of India on 25 June 2015. It selected 100 cities through four rounds of competition between January 2016 and June 2018.
- The Ministry of Housing and Urban Affairs (MoHUA) reports that all 100 Smart Cities have an operational Integrated Command and Control Centre (ICCC), stated as of 31 March 2025.
- The mission was extended to 31 March 2025, and MoHUA describes it as completed on that date. As of 9 May 2025, 7,555 of 8,067 mission projects (94%) were complete.
- MoHUA's Advisory No. 27, announced on 10 June 2025, says city special purpose vehicles (SPVs) and ICCCs should keep operating beyond the mission, with operation and maintenance plans for mission assets.
- The Urban Challenge Fund, approved by the Union Cabinet in February 2026 with Rs 1 lakh crore of central assistance, is the main new central urban programme. It works differently: central assistance covers 25% of a project and at least 50% must come from the market.
What was the Smart Cities Mission?
The Smart Cities Mission was a central programme to improve the quality of life in 100 Indian cities through infrastructure and technology projects. The Government of India launched it on 25 June 2015. MoHUA selected the 100 cities through four rounds of competition, from January 2016 to June 2018.
Each city followed two approaches. Area-based development improved one defined part of the city, chosen with citizen participation. Pan-city projects applied technology-driven solutions across the whole city. Each city set up a special purpose vehicle under the Companies Act, 2013, owned 50:50 by the state or union territory and the urban local body (ULB), to plan and deliver the projects.
The central government's allocated budget for the mission was about Rs 48,000 crore. MoHUA reported that 99.44% of the budgeted outlay had been released to the 100 cities by 31 March 2025, with states, ULBs and partnerships funding the rest of an investment of about Rs 1.64 lakh crore.
What was a Smart City ICCC meant to do?
A Smart City ICCC was meant to give each city one centre where departments see the same live picture of the city and coordinate their response. In a Lok Sabha reply on 10 August 2023, MoHUA described ICCCs as the 'brain and nervous system' for city operations, and named inter-departmental coordination as one of their main features.
The same reply lists the departments integrated with ICCCs: traffic police, health, water, solid waste management and irrigation. It calls integration with the police department one of the most important achieved in most cities, and says efforts were under way to link ICCCs with CCTNS, the Crime and Criminal Tracking Network and Systems. During the COVID-19 pandemic, MoHUA reports, ICCCs also served as city war rooms.
To help cities buy ICCCs, a Model ICCC RFP (request for proposal) was developed in 2016, and Model RFP 2.0 was released in 2021, according to CERT-In's cyber security guidelines for smart city infrastructure. What an ICCC connects, layer by layer, is covered in our note on what an ICCC integrates.
How many ICCCs are operational, according to MoHUA?
MoHUA reports that all 100 Smart Cities have operational ICCCs. It said so in a Lok Sabha reply on 10 August 2023, and again in a PIB note of 24 June 2025 that gives the position as of 31 March 2025.
'Operational' is MoHUA's word, and it does not say how many systems each centre integrates or how many departments work from it. The same note says traffic enforcement systems for red-light violations and automatic number plate recognition (ANPR) were installed, and that intelligent traffic management systems (ITMS) are monitored through ICCCs. The figures in the table are MoHUA's, as published.
| Item | Reported figure | As of |
|---|---|---|
| Cities with an operational ICCC | All 100 | 31 March 2025 |
| Projects completed | 7,555 of 8,067 (94%) | 9 May 2025 |
| Central budget released | 99.44% of outlay | 31 March 2025 |
| CCTV surveillance cameras | Over 84,000 | 31 March 2025 |
| Emergency call boxes | 1,884 | 31 March 2025 |
| Public address systems | 3,000 | 31 March 2025 |
| Water network on SCADA | Over 17,026 km | 31 March 2025 |
When did the Smart Cities Mission end?
The Smart Cities Mission ended on 31 March 2025. On 3 July 2024 MoHUA announced that the mission period had been extended to that date so cities could finish the remaining 10% of projects, without any money beyond the approved allocation. MoHUA's advisory of 10 June 2025 refers to the completion of the mission on 31 March 2025.
Not every project was finished by then. MoHUA reported that as of 9 May 2025, 7,555 of the 8,067 projects (94%) were complete, worth Rs 1,51,361 crore, and 512 projects worth Rs 13,043 crore were in advanced stages of implementation. Those remaining projects sit with the city SPVs and the states, which the June 2025 advisory asks to complete them on time.
What happens to SPVs and ICCCs now?
MoHUA's position is that both should keep running. Its Advisory No. 27, announced on 10 June 2025, says the Government of India is of the view that SPVs and ICCCs should continue to operate beyond the mission. It asks every SPV to finish ongoing mission projects and to prepare detailed operation and maintenance (O&M) plans for the assets the mission created.
For ICCCs, the advisory says they are to be used as city operating systems and state analytical hubs, with operational control preferably kept by the urban development departments. SPVs may earn service-linked revenue for managing ICCC functions. States are encouraged to integrate more city services into their ICCCs and to upgrade them on time. The advisory names five areas for SPVs' future work.
- Technology support: cyber hygiene, analytics, data systems and running ICCCs
- Project implementation: acting as implementing agency for central and state schemes, with a charge of 1.5% to 3% as per state norms
- Consulting support to ULBs and state departments
- Research and assessment, including acting as incubation hubs for urban technology start-ups
- Investment facilitation for city-level economic development
What comes after the Smart Cities Mission?
The main new central programme for cities is the Urban Challenge Fund (UCF). Announced in the Union Budget 2025-26, it was approved by the Union Cabinet with total central assistance of Rs 1 lakh crore, as reported by PIB on 14 February 2026. It runs from FY 2025-26 to FY 2030-31, with implementation extendable to FY 2033-34.
The UCF works differently from the Smart Cities Mission. Central assistance covers 25% of a project's cost, and at least 50% must be raised from the market, through municipal bonds, bank loans or public-private partnerships. Projects are chosen in challenge mode under three verticals: Cities as Growth Hubs, Creative Redevelopment of Cities, and Water and Sanitation.
Security is the other thread. MoHUA issued advisories on cyber security for smart city infrastructure and ICCCs (Advisories No. 22, 24 and 25), and CERT-In's guidelines for smart city infrastructure include a section on operational security for command and control centres. Those guidelines say ICCC logs should be forwarded to a central server and maintained as per CERT-In's directions of 28 April 2022.
What should a city check before upgrading or re-tendering its ICCC?
A city should first find out what it owns and what still works. The mission that paid for the ICCC has ended, and each contract, licence and piece of hardware has its own end date.
- When each O&M contract and software licence ends, and who holds it: the SPV, the ULB or the state
- An inventory of every integrated system, and whether each integration still works today
- Whether the city owns the data, the configurations, the interface documentation and the administrator passwords
- The age of cameras, servers, storage and the video wall, and which are near end of support
- A cyber security audit against MoHUA's ICCC advisories and CERT-In's directions
- Who funds operators on every shift once mission money has ended
- Which new services the city wants to integrate, as the June 2025 advisory encourages, and which departments' procedures must change to use them
How Ahuva approaches ICCC work
Ahuva has built command and control centres since 2015, when it delivered its first, for a major port project at Visakhapatnam. Its ICCC scope covers centre design, video walls, consoles and AV, and the integration of CCTV, GIS, IoT, SCADA and analytics, with incident management. It is currently delivering the integrated command and control centre for Project Sarthi for the Greater Visakhapatnam Municipal Corporation, contracted via KELTRON.
Frequently asked questions
- When was the Smart Cities Mission launched?
- The Government of India launched the Smart Cities Mission on 25 June 2015. The 100 cities were chosen through four rounds of competition between January 2016 and June 2018.
- Is the Smart Cities Mission still running in 2026?
- No. The mission ended on 31 March 2025 after one extension. MoHUA has asked states to keep city SPVs and ICCCs running and to complete remaining projects.
- How many smart cities have an operational ICCC?
- MoHUA reports that all 100 Smart Cities have operational ICCCs, as of 31 March 2025. The figure does not describe how many systems or departments each centre integrates.
- Who runs a Smart City ICCC after the mission?
- MoHUA's Advisory No. 27 says operational control of ICCCs should preferably stay with the state urban development departments, and that SPVs may earn service-linked revenue for managing ICCC functions.
- Does the Urban Challenge Fund replace the Smart Cities Mission?
- It is the main new central urban programme, but it is a different model. Central assistance covers 25% of a project's cost and at least half must be raised from the market.
Sources
- 10 Years of Smart Cities Mission (Explainer, 24 June 2025) · Press Information Bureau, Ministry of Housing and Urban Affairs
- Integrated Command and Control Centres (Lok Sabha reply, 10 August 2023) · Press Information Bureau, Ministry of Housing and Urban Affairs
- Smart Cities Mission extended till March 2025 (3 July 2024) · Press Information Bureau, Ministry of Housing and Urban Affairs
- MoHUA issues Advisory for Repurposing of Smart City SPVs (10 June 2025) · Press Information Bureau, Ministry of Housing and Urban Affairs
- Cabinet approves Rs. One Lakh Crore Urban Challenge Fund (14 February 2026) · Press Information Bureau, Cabinet
- Cyber Security Guidelines for Smart City Infrastructure · CERT-In
Related
- What an ICCC actually integrates, and what it does not →
- What a command centre or ELV tender asks for at pre-qualification →
- One integrator or many vendors: design-build-operate-maintain →
- Projects →
- CERT-In directions 2022: 6-hour incident reporting and 180-day log retention →
- Control room video walls: LCD vs direct-view LED vs rear-projection cubes →
Scoping a system like this? Talk to the team that designs, builds and maintains it.
Contact us